Name
The task's current name will be displayed in this column.
Current Start
The start date of the task as it is currently scheduled in the project.
Current Finish
The finish date of the task as it is currently scheduled in the project.
Current Duration
The duration of the task, rounded to the next whole hour, as it is currently scheduled in the project.
Calendar Chart
The task, as scheduled at the time the baseline's creation and as currently scheduled, is plotted in a calendar for quick comparison.
Baseline Start
The start date of the task as it is was scheduled in the project when the baseline was created.
Baseline Finish
The finish date of the task as it is was scheduled in the project when the baseline was created.
Baseline Duration
The duration of the task, rounded to the next whole hour, as it was scheduled in the project when the baseline was created.
Variance
The duration, rounded to the next whole hour, by which completion of the task has changed since the baseline was created. A positive value indicates that the task has a later finish date in the project than in the baseline. A negative value indicates an early finish.